0004 - site office for remote sites

Last changed: 2019/11/15 11:42 

25th of September, 2018

Has been dismantled, due to need to relocate from present site.

3rd of May, 2018

Amendment 0004 - power and water for site office

1st of April, 2017

Interclamps purchased and collected - http://fatbandicoot.soilmagic.com.au/uploads/Interclamp-Proforma_202023_17-02-21_09-07.pdf

Steel pipe ordered and delivered - http://fatbandicoot.soilmagic.com.au/uploads/Springvale_Steel-FEMAIL1BUILD533.PDF

Spent four hours erecting the frame this afternoon. About 50% done.

16th of February 2017

Amendment passed by the Planning Subcommittee, funding the construction of a galvinised roof and annex - Amendment - site office roof

8th of December, 2016

Approved by the Planning Subcomittee! - Proposal - site office